Implementation of Project Management Practices in the Direct Purchasing System of a Company

Abstract:

Throughout the years, project management has been essential to the success of projects in organizations and if it is implemented correctly, it can help to achieve the demanding, urgent and competitive goals that companies are experiencing. This presents an implementation and adaptation of project management practice to the projects from the purchasing section of a company where the employees have to manage people, information and resources. The implementation was developed considering the projects associated to the nomination of a supplier and the mechanical parts approval. It was used the project management standard from project Management Institute (PMI).The research has shown, using PERT , that the expected duration of this type of projects is about 446 days and the probability of finishing a project within a year is only about 10% . Due to time constraint, it was not possible to complete several action research cycles and verify its actual benefits.

nsdlogo2016